IceCube: Project Timeline

May 2004
- IceCube Construction Project Baseline and U.S. National Science Board Construction Funding Approval

June 2004
- UW Milestone - Validate Digital Optical Module Requirements for First Year Deployment

July 2004
- UW Milestone - Conduct DOM Production Readiness Review for Initial Strings and Tanks

August 2004
- Complete EHWD System Integration, Verification, and Testing

September 2004
- UW Milestone - First Digital Optical Module Accepted and Ready for Shipment

December 2004
- UW Milestone - Complete Shipment of EHWD Equipment to the South Pole
- Deploy initial IceTop Tanks

January 2005
- Construction Status - 1 String and 8 Tanks Deployed
- Assemble and Operate the Enhanced Hot Water Drill at the South Pole
- Deploy Initial In-Ice Strings
- UW Milestone - Complete Assembly EHWD at the South Pole

February 2005
- UW Milestone - Begin End-to-End System Tests of Initial Strings and Tanks

April 2005
- UW Milestone - Collect and Process Data with Initial Strings and Tanks

May 2005
- Complete End-to-End System Tests of Initial Strings and IceTop Array

January 2006
- Construction Status - 9 Strings and 32 Tanks Deployed

February 2006
- Determine Annual String Deployment Rates for Future Years
- UW Milestone - Perform Initial In-Ice and IceTop Data System Integration

March 2006
- UW Milestone - Validate Digital Optical Module Requirements

June 2006
- Establish Full Production Rate of Digital Optical Modules

September 2006
- UW Milestone - Approve full production contracts for DOM and DAQ Components

November 2006
- Validate In-Ice and IceTop Design

December 2006
- UW Milestone - Beneficial Occupancy of the IceCube Laboratory

January 2007
- Construction Status - 22 Strings and 52 Tanks Deployed
- Full Occupancy of the IceCube Laboratory

March 2007
- Initial Operational and Data Analysis Capability
- UW Milestone - Complete AMANDA/IceCube Integration
- UW Milestone - Compete Detector Verification and Physics Benchmarking for Initial Operations

August 2007
- Data System Software Complete

January 2008
- Construction Status - 40 Strings and 80 Tanks Deployed

June 2008
- Complete Integration of In-Ice and IceTop Data Systems

January 2009
- Construction Status - 59 Strings and 120 Tanks Deployed

January 2010
- Construction Status - 77 Strings (6 Deep Core) and 148 Tanks Deployed

January 2011
- Construction Status - 86 Strings and 160 Tanks Deployed